Kaber Court Re-Roof Project, Liverpool

The Kaber Court development in Liverpool, consisting of four blocks, experienced multiple leaks from its flat roof system. This prompted a detailed investigation into the roof's condition and the creation of a cost-effective solution to address the problem. A phased re-roofing program was initiated, utilising advanced moisture mapping technology to guide the process and ensure long-term protection for the property. 

Kaber Court Re-Roof Project, Liverpool

Project Details

After a comprehensive investigation of the roof system, moisture mapping technology was used to identify areas of water ingress and assess the extent of moisture spread across the four blocks. The condition report revealed that the roof had reached the end of its serviceable life, with numerous ingress points contributing to the leaks. To determine the best course of action, core samples of the roof were taken to evaluate its composition.

By working closely with surveyors and a leading roofing product manufacturer, it was discovered that the roof's insulation remained unaffected by the moisture. This finding enabled us to recommend a cost-effective overlay solution rather than a full roof replacement, saving significant costs for the client while still offering a full 20-year warranty.

Given the roof’s 20 varying levels, a phased three-year overlay program was developed to address the most critical areas first. Using moisture mapping data to guide the process, the project was tendered to a series of accredited contractors, all qualified to install the specified roofing system while maintaining the 20-year warranty. 

Project Phases & Outcome

The first phase of the project began in the summer of 2024 and is progressing smoothly. This phase has focused on addressing the areas most impacted by water ingress, ensuring the building’s fabric remains protected while Minimising disruption to residents. The phased approach will continue over the next two years to ensure the entire roof is fully overlaid and protected. 

Key Achievements

  • Cost Savings: The use of an overlay system instead of a full replacement saved the client substantial costs while ensuring a durable, long-term solution.
  • Innovative Technology: Utilisation of moisture mapping technology to accurately assess the roof’s condition and guide the phased re-roofing process.
  • Warranty Protection: The project provides a full 20-year warranty, ensuring peace of mind for the property’s owners and long-term protection for Kaber Court.
  • Phased Approach: A carefully planned, phased installation to Minimise disruption and ensure efficient project completion over a three-year timeline. 

The Kaber Court re-roof project demonstrates our commitment to delivering effective, long-term roofing solutions tailored to the needs of our clients. By leveraging innovative technology and working closely with trusted contractors, we have provided a cost-effective and durable roofing solution for this complex development. 